From storm damaged to lesson ready
Behind the 72-hour mission to get Kempsey High School operational.
15 August 2025
On the first weekend in August, storms tore through the NSW Mid North Coast, severely damaging Kempsey High and other local schools. Fierce winds ripped off part of a roof at Kempsey High and flooded rooms.
Debris littered the grounds, power lines had snapped, and the school had to close for safety reasons.
An extraordinary team effort saw the Kempsey High community and the NSW Department of Education swing into action to ensure the school was able to re-open as quickly as possible.
As a result, it is smooth sailing ahead for Kempsey High’s trial HSC exams starting next week, Director, Educational Leadership, Melinda Brady said.
“They’ll run from Monday 18 August through to Tuesday 26 August,” Ms Brady said.
Regional Director, North Coast, Brad Townsend said the remarkable effort showed what is possible when a dedicated team are backed by robust processes and genuine care for the students and community.
“That depth of support and expertise backs every one of our schools,” Mr Townsend said.
“Not just during emergencies, but every single day. Thank you to the team who worked tirelessly to reopen Kempsey High School.”
All hands on deck: 72 hours before reopening
While the rain and strong winds continued, the Asset Management and Facilities Management teams were already mobilising. Despite the conditions, they were:
assessing the full extent of damage to Building A and other areas around the school
coordinating with the school team, including Principal Simon McKinney, on immediate priorities
arranging power disconnection to affected areas with safety in mind
requesting the delivery of three demountables to serve as temporary learning spaces.
Solutions and action: 48 hours before reopening
By Tuesday morning, the work was already underway. The team coordinated closely to oversee:
emergency roof repairs with heavy duty tarpaulins securing the exposed roof
temporary safety fencing installed to contain damaged areas
the restoration of power to the administration floor and unaffected classrooms
arborists clearing dangerous trees and branches
testing by independent hygienists in exposed areas for hazardous materials
removal of debris from trees and grounds.
The final push: 24 hours before reopening
Wednesday was the final sprint to the finish line, and every detail mattered:
Safety tests confirmed no hazardous materials were disturbed in the affected areas
Power line and debris removal were completed
Deep cleaning of water-affected spaces
Final site clearance ensuring all areas were safe for the return of students and staff
A new timetable created to redistribute classes across unaffected spaces.
Welcome back: the reopening
On Thursday 7 August, students and staff returned to a fully operational school.
The ground administration floor and unaffected classrooms of Building A reopened and the new timetables meant every student could resume learning.
- News